# Consolidated Audit Review
Status: initial scope selected; efficiency and structural-refactoring scope
remain under review. Implementation has not begun.
Status: initial scope and four localized efficiency improvements selected;
collection-policy and structural-refactoring scope remain under review.
Implementation has not begun.
Consolidated: 2026-10-25. Baseline: `ecd5d5d`.
This document consolidates nine sequential audits for maintainer review. It owns
@@ -20,8 +21,8 @@ product fixes.
The 35 original numbered findings map to 31 review entries after deduplication
and integration of related test work. All findings remain unresolved; the
[settled scope decision](#oq-1-what-should-the-first-implementation-scope-include)
identifies the selected work. OQ-2 and OQ-3 remain open.
[settled scope decisions](#settled-scope-decisions) identify the 25 selected
entries. OQ-3 remains open, covering E01/E02 and the four broader refactors.
Their medium/low priorities retain the original assessments; those labels do not
imply severity certification or implementation order. IDs remain stable as work
is selected or completed.
@@ -908,38 +909,53 @@ boundaries. Delivering defects first and cleanup separately would reduce the
initial review surface, but would retain redundant work and revisit those
boundaries. The combined approach is selected.
The six efficiency candidates and four broader structural refactors remain
unselected pending OQ-2 and OQ-3. This decision does not select new public behavior
or establish an implementation sequence.
## Open Questions
Efficiency and broader structural choices are addressed separately below. This
decision does not select new public behavior or establish an implementation
sequence.
### OQ-2. Which Efficiency Candidates Should Accompany Remediation?
**Recommendation:** consider E04/E05 as narrow local improvements, and A05/F08
as lower-priority options after their correctness/diagnostic boundaries are sound.
Evaluate E01/E02 together with E03 before committing to a policy-state redesign:
their distinct scaling cases need preserved acceptance even if they share an
implementation. These candidates have source-level evidence of avoidable work,
but no new measured speedup claim.
**Settled:** include the four localized efficiency improvements below. Decide
E01/E02 together with collection-policy preparation and evidence ownership (E03)
under OQ-3; those two efficiency candidates remain unselected.
**Alternative:** defer all six efficiency candidates until representative consumer
profiling establishes their practical cost. This concentrates the first effort
on correctness and cleanup, at the cost of retaining demonstrated growth patterns.
It does not block C02's availability fix or A04/D01's enforcement of existing
resource budgets. Broader experiments in `future.md` remain separately deferred.
| Selected improvement | Scope and dependency |
| --- | --- |
| E04: tier-history projection lookups | Reuse a local lookup index or equivalent traversal while preserving authored coordinates and projection evidence. |
| E05: compound identity restoration | Avoid repeated mapping scans while preserving child identity, mapping order, and detached nodes. |
| A05: dynamic-type eligibility reuse | Reuse only completed successful checks within the operation, after A02 repairs descriptor construction failure state. |
| F08: secret-failure location lookup | Include at lower priority; prepare lookup state lazily so successful loads avoid unnecessary indexing. |
Together with OQ-1, this selects 25 review entries. These local changes address
source-demonstrated repeated work without requiring public APIs, persistent
caches, or a new architectural model. Preserve their behavioral acceptance
cases and keep implementation proportionate. E01/E02 involve policy retirement
timing and mutable ownership, so their scope belongs with the E03 discussion.
Deferring all six until consumer profiling was considered. That would reduce
initial scope and avoid optimizing uncommon workloads, but would retain known
growth patterns with relatively direct remedies in the four selected cases.
The selected approach does not promise a measured startup improvement; practical
benefit depends on configuration shape and workload. Broader experiments in
[future.md](future.md#3-performance-experiments) remain deferred. C02's availability
fix and A04/D01's existing-budget enforcement remain selected independently.
## Open Questions
### OQ-3. How Much Structural Refactoring Should Be Selected?
F01's removal of the test-only protocol is already selected under OQ-1.
OQ-2 leaves E01/E02's policy retirement and copying improvements for this decision,
alongside E03's policy preparation and evidence responsibilities. Their distinct
scaling cases must remain visible even if implemented together.
**Recommendation:** assess active acquisition handoffs (F02) and policy/evidence
ownership (E03) with their affected fixes before selecting a wider extraction. Leave glob
entry extraction (C03) and transport simplification (F07) optional unless a
concrete design reduces concepts and clarifies ownership.
ownership (E03), including E01/E02, with their affected fixes before selecting a
wider extraction. Leave glob entry extraction (C03) and transport simplification
(F07) optional unless a concrete design reduces concepts and clarifies ownership.
**Alternative:** include all four structural refactors in the same effort for a
more uniform maintenance result. This offers broader readability improvements
**Alternative:** include all four structural refactors alongside E01/E02 in the
same effort for a more uniform maintenance result. This offers broader readability improvements
but increases review scope and the chance of moving complexity rather than
removing it. Neither approach calls for a new public API, generic framework, or
changes to the established configuration model.