Verify the integrated application and complete the migration
This commit is contained in:
@@ -2,9 +2,9 @@
|
||||
|
||||
**Last updated:** 2026-09-24
|
||||
|
||||
**Status:** Final target selected; production implementation pending. The boundary
|
||||
and selected overlays are verified. The [implementation plan](implementation.md)
|
||||
owns execution stages; no production migration or release has begun.
|
||||
**Status:** Production implementation complete. The selected configuration and
|
||||
overlay model is implemented; [implementation evidence](implementation.md)
|
||||
records verification. No release has been published.
|
||||
|
||||
## Purpose and Direction
|
||||
|
||||
@@ -20,15 +20,14 @@ guide instead of legacy loaders, aliases, dual operating modes, or an ongoing
|
||||
compatibility layer. Retain existing syntax only when it independently suits the
|
||||
new model, not because compatibility requires it.
|
||||
|
||||
The initial review and prototype used ConfigKit v0.3.1. The prototype now pins
|
||||
v0.4.0 and verifies its selected-overlay path; original v0.3.1 findings remain
|
||||
historical. The installed
|
||||
application must depend on a versioned module, not a sibling checkout or local
|
||||
module replacement.
|
||||
The initial review and prototype used ConfigKit v0.3.1, then verified v0.4.0
|
||||
selected overlays. Those findings remain historical; the prototype was removed
|
||||
after production integration. The application depends on a versioned module,
|
||||
without a sibling checkout or local module replacement.
|
||||
|
||||
The shared boundary/prototype unit is complete. Its [selected contract, inventory,
|
||||
and evidence](library-boundary-findings.md) define the detailed target alongside
|
||||
this roadmap. Production configuration migration has not begun.
|
||||
this roadmap. Production configuration migration is complete.
|
||||
|
||||
## Target End State
|
||||
|
||||
|
||||
@@ -2,7 +2,7 @@
|
||||
|
||||
**Last updated:** 2026-09-24
|
||||
|
||||
**Status:** Ready for implementation. All stages below are pending. This replaces
|
||||
**Status:** Implemented. All twelve stages are complete. This replaced
|
||||
the completed testing-overlay prototype plan; its results remain in the
|
||||
[boundary findings](library-boundary-findings.md#selected-overlay-extension-2026-09-24).
|
||||
|
||||
@@ -583,7 +583,21 @@ belongs to Stage 12.
|
||||
|
||||
## Stage 12: Verify the Combined Application and Close the Refactor
|
||||
|
||||
**Status:** Pending. **Depends on:** Stages 1–11.
|
||||
**Status:** Complete. Controlled HTTP subprocess tests passed for base and testing
|
||||
overlay selection, explicit validation-profile and domain overrides, both outbound
|
||||
models, accepted repair, domain rejection without semantic retry, warning-only
|
||||
repair exhaustion, empty and repeated module pipelines, and safe partial failure
|
||||
diagnostics. `go test ./...`, `go build -o ./bin/audita ./cmd/audita`, focused
|
||||
race tests for runtime/runner/subprocess code, and both Linux release builds
|
||||
passed. The full suite also passed under Go 1.25.5 with offline module access.
|
||||
Maintained examples and local documentation links validated; `git diff --check`
|
||||
passed. No native macOS or live provider call was run. Release preparation remains
|
||||
separate: propose Audita v2.0.0 with [one migration guide](../migrations/v2.md),
|
||||
the actual pinned production dependency/license inventory, and LGPL
|
||||
notice/source/rebuild-distribution review before publication. No release was
|
||||
published here.
|
||||
|
||||
**Depends on:** Stages 1–11.
|
||||
**Owns:** final integration tests, final defect fixes within this scope, and status/evidence.
|
||||
|
||||
1. Complete representative production subprocess workflows against controlled HTTP:
|
||||
|
||||
@@ -2,10 +2,9 @@
|
||||
|
||||
**Last updated:** 2026-09-24
|
||||
|
||||
**Status:** Final target selected; production implementation pending. The shared
|
||||
boundary and offline prototype, including ConfigKit v0.4.0 overlays, are verified.
|
||||
[Implementation stages](implementation.md) are owned by the implementation plan.
|
||||
This roadmap defines the end state and user intent; it authorizes no publication.
|
||||
**Status:** Production implementation complete. ConfigKit v0.4.0 and PromptKit
|
||||
v0.11.0 are adopted; [implementation evidence](implementation.md) records the
|
||||
completed checks. Release compliance and publication remain separate work.
|
||||
|
||||
## Goal and Ownership
|
||||
|
||||
|
||||