**Last updated:** 2026-09-24
|
||||
|
||||
**Status:** Planned. All stages below are pending. This plan implements the next
|
||||
**Status:** Complete (2026-09-24). All six stages below are finished. This plan implements the next
|
||||
unit in the [prototype roadmap](library-boundary.md#next-unit-testing-overlays-and-production-migration-plan),
|
||||
not the production ConfigKit or PromptKit migrations.
|
||||
|
||||
@@ -249,7 +249,10 @@ to a passing test or observed demonstration result. Verify affected links and
|
||||
|
||||
## Stage 6: Prepare the Production Migration Plan and Close the Unit
|
||||
|
||||
**Status:** Pending. **Depends on:** Stage 5.
|
||||
**Status:** Complete (2026-09-24). **Depends on:** Stage 5. The ordered ConfigKit
|
||||
production handoff records bounded packages, interim runtime behavior, tests,
|
||||
dependencies, and acceptance criteria. Prototype evidence and scope audit passed;
|
||||
links and `git diff --check` verified.
|
||||
|
||||
Expand `configkit.md` into a concrete, ordered production migration plan using
|
||||
the existing inventory and verified overlay evidence. Follow the development
|
||||
|
||||