Plan production ConfigKit migration from verified prototype

This commit is contained in:
2026-09-24 00:27:47 +00:00
parent 590604bf38
commit 5b7d2e6e81
5 changed files with 204 additions and 37 deletions

View File

@@ -2,7 +2,7 @@
**Last updated:** 2026-09-24
**Status:** Planned. All stages below are pending. This plan implements the next
**Status:** Complete (2026-09-24). All six stages below are finished. This plan implements the next
unit in the [prototype roadmap](library-boundary.md#next-unit-testing-overlays-and-production-migration-plan),
not the production ConfigKit or PromptKit migrations.
@@ -249,7 +249,10 @@ to a passing test or observed demonstration result. Verify affected links and
## Stage 6: Prepare the Production Migration Plan and Close the Unit
**Status:** Pending. **Depends on:** Stage 5.
**Status:** Complete (2026-09-24). **Depends on:** Stage 5. The ordered ConfigKit
production handoff records bounded packages, interim runtime behavior, tests,
dependencies, and acceptance criteria. Prototype evidence and scope audit passed;
links and `git diff --check` verified.
Expand `configkit.md` into a concrete, ordered production migration plan using
the existing inventory and verified overlay evidence. Follow the development