@@ -1,6 +1,6 @@
|
||||
# Implementation Plan: Import Discovery and Dependency-Ready Ordering
|
||||
|
||||
Status: Stages 1–2 complete; 17 implementation stages remain.
|
||||
Status: Stages 1–3 complete; 16 implementation stages remain.
|
||||
|
||||
## Authority, baseline, and execution
|
||||
|
||||
@@ -270,6 +270,11 @@ to describe implemented scheduling, linking ADR 0015.
|
||||
Acceptance: inheritance and facade inheritance suites pass; final values,
|
||||
presence, origins, and explanation agree; no alternate resolver remains.
|
||||
|
||||
Completion: implemented in commit `6e40c16` (`Schedule sibling inheritance by
|
||||
dependency readiness`). Verified with engine inheritance and facade inheritance
|
||||
tests, `./scripts/check.sh`, and `git diff --check`. Nested scope discovery,
|
||||
projection budgets, and retained evidence remain in their existing owners.
|
||||
|
||||
## Stage 4 — Retain the import inclusion graph during acquisition
|
||||
|
||||
Refactor `imports.go` and `load_input.go` so acquired contributions carry stable
|
||||
|
||||
Reference in New Issue